September 23, 2023
by Mike McDevitt
The underground work is largely completed. The asphalt team has moved in to begin grading and setting elevations for the new asphalt and cement work to come. We have been blessed with good weather and look forward to making a lot of progress this week. If all goes well we hope to be putting down asphalt the last week of September.
Read More
-
September 13, 2023
by Mike McDevitt
The Rectory Parking Lot recently had new asphalt installed and new cement was poured along Charlevoix to complete the driveway apron and repair areas in front of the flagpole. Fr. Andrew is happy to have his garage back and a place to safely store his car. The completion of this small lot provides a glimmer of hope that our big lot is soon to follow. The underground team will be wrapping up their storm water detention system installation this week. We look forward to the paving team’s arrival to prepare the lot asphalt installation.
Read More